Client: Coombs Construction
Works: Drop in centre for the East Sussex Hospital trust. I beam panels incorporating full Warmcel insulation
Value: £200,000
Duration: 6 week
Sector: Hospitals
Ofp completed the visitor centre at The Conquest Hospital, St. Leonards-on-Sea for the East Sussex Health Authority early 2008. Built to supplement the existing day centre services, the design comprised of a large sloped roof filled with Warmcel insulation to provide excellent acoustic and thermal performance. The curved façade provided an interesting and ‘welcoming’ look designed to blend in with the existing facility. All works were completed within both budget and timescale and the BBA Accredited in-house Warmcel team took a mere 4 days to complete the filling of the external walls.